Acceleration Pressure
Programme acceleration requirements may increase construction costs and introduce additional coordination challenges.
- Home
- Case Studies
- Acceleration Pressure
Case Details
Project Type
Residential led mixed use block
Project Stage
Mid construction, following early delay
Consultant Role
Independent commercial and programme advisor
Digital Tools Used
Delay trend review and productivity analysis
Client Category
Developer
Discuss Your Project
If you are planning a residential development or complex construction project, early commercial clarity can significantly reduce cost risk and procurement uncertainty.
Our digital construction advisory helps developers and project teams verify quantities, review procurement strategy and improve cost certainty before construction begins.
Address Business
London,W1T 2EW
Contact With Us
Email :office@reltic.co.uk
Working Time
Holiday : Closed
Chasing Lost Time at Any Cost
When a project starts to drift, the first reaction is often to “push the programme” rather than understand why progress has slipped. Extra labour is added, more areas are opened at once and weekend working becomes routine. Without a clear commercial and technical basis, this kind of acceleration rarely delivers the recovery hoped for. It can actually increase disruption, claims and tension with funders or occupiers.
This scenario shows how a structured review of delay, productivity and commercial options helped a client respond to schedule pressure in a controlled way rather than agreeing to open‑ended acceleration demands.
Typical Project Context
Acceleration pressure is particularly common on:
In these situations, pressure to recover time is real, but so is the risk of agreeing to measures that are expensive, difficult to evidence and only partially effective.
Key Challenges
1. Blurred line between recovery and change
By the time we became involved, several months of slippage had built up. The contractor proposed additional shifts, out of hours working and opening more floors at once as an “acceleration strategy”. The difficulty was that:
- not all delay was clearly attributable to the employer
- some slippage arose from productivity and coordination issues within the contractor’s control
- the cost and likely benefit of the proposed measures had not been quantified
The developer needed clarity on what they were being asked to pay for and whether it would genuinely recover time.
2. Programme logic not reflecting actual progress
The live programme still showed the original completion date, with numerous activities overlapped and compressed to make the dates work. Links had been adjusted piecemeal, rather than through a considered resequence. That made it difficult to see:
- which parts of the delay could be traced to particular events
- which areas had realistic scope for recovery
- where further compression would simply create more disruption and claims
Issues overlapped with the themes covered in Programme Sequencing Risk and Site Logistics Constraints, but here the trigger was explicit pressure to accelerate.
3. Commercial exposure from informal agreements
Discussions about extra shifts, increased supervision and weekend working had already started. Some additional resource was on site, but no formal agreement captured:
- the basis of entitlement to extra cost
- how success would be measured
- what would happen if acceleration did not achieve the targeted dates
The client faced the prospect of paying more without securing either time certainty or protection against later disputes, including those that might ultimately fall into Final Accounts & Disputes .
Delay and Productivity Review
We began by reviewing how delay had arisen to date. Using site records, progress reports and the existing programme, we:
- identified the main events and trends that had caused slippage
- separated employer‑related causes from contractor and neutral causes
- examined productivity data in key trades to see where output had fallen short of expectations
This established a factual baseline. It showed that some delay was linked to late design and client changes, touching issues seen in Incomplete Design Information and Late Design Changes, while other delay came from internal coordination and resourcing decisions by the contractor.
Testing Acceleration Options
With a clearer picture of the causes of delay, we then evaluated proposed acceleration measures. Working with the project team and applying the commercial discipline used in Construction Cost Control , we considered for each option:
- specific changes to resource levels, working hours or sequencing
- realistic impact on activity durations and critical path dates
- direct and indirect cost, including supervision and preliminaries
Options ranged from modest increases in targeted trades to more intensive proposals such as additional shifts on core paths. Some options offered good value in terms of time gained per pound spent; others were shown to add cost while risking further disruption.
Commercial Framework for Acceleration
Where the client wished to proceed with selected measures, we helped set up a clear commercial framework, aligned with principles used in Variation Control . This included:
- defining which measures were employer instructed acceleration and which were simply the contractor meeting existing obligations
- agreeing how additional cost would be calculated and evidenced
- setting interim milestones and progress indicators so that effectiveness could be reviewed
This made it easier to control expenditure, avoid duplication of payment and keep both parties aligned on the purpose and scope of acceleration.
Outcomes for the Client
By responding to acceleration pressure in a structured way, rather than under urgency alone, the client achieved:
- a clearer understanding of why delay had occurred and which elements they were responsible for
- a targeted set of acceleration measures with quantified cost and realistic time benefit
- contractual clarity that reduced the risk of later disagreement over entitlement and quantum
- improved visibility for funders on how recovery of the completion date was being managed
The project continued with tighter control of both time and money, and with a reduced chance that acceleration itself would become a further source of dispute.
Discuss Your Project
If you are being asked to fund acceleration to recover lost time, but you are not confident that the proposals will deliver what is promised, it may be worth stepping back before you commit.
We can combine delay and productivity analysis with Construction Cost Control , structured change management under Variation Control and, where necessary, support from Final Accounts & Disputes to help you understand your true exposure and options.
Use the form below to outline your project, current programme status and any acceleration proposals already on the table. We will respond with a focused review scope tailored to your scheme.
